Project Detail
Construction giant Pindan was awarded the contract for a new shopping development in Ellenbrook city centre comprising of retailers such as First Choice liquor, Cheese Cake Shop, and Pet Stock for the first stage and new supermarket chain Aldi for a second development stage.
The complete project was estimated at almost $9 million and the first stage earthworks to be completed by March 2016, and stage 2, completed by August 2016 ready for the retailer shop fit outs and operation to commence.
Allday construction provided the complete earthworks package for both stages including extensive car park works.
Mobilizing to site in late September 2015, both stages were completed to deadline.
Scope of works included
⦁ Clear vegetation, create access tracks
⦁ Remove 1000m3 fill to balance site (stage 2)unsure of stage 1?
⦁ Box out of car parks
⦁ Final trim and compaction of pad ready for build
⦁ Import over 5000m3 of roadbase and limestone materials
⦁ Provide 1000m2 hard stand at 150mm of limestone- stage 2 only- do you know stage 1 car park size?
⦁ Compact and supply Asphalting, Kerbing and Linemarking
⦁ Final Site clean
Machines utilized on project
⦁ 2x Wheel Loader – Komatsu WA380
⦁ Water Truck
⦁ Rollers- Padestrian, Padfoot and Smooth Drum
⦁ Bobcat – T870 track machine
⦁ Bobcat – S185 wheel machines
⦁ Bobcat – T590 Track Machines
⦁ Compactors